1. Task A can start immediately and has a 4 day duration. Task B can start after A is complete and has a 7 day duration. Task C can start when A is complete and has a 5 day duration. Task D can start when B and C are complete and has a 6 day duration. Task E can start when D is complete and it has a 3 day duration. What is the duration of the project? (1015)