CAPMDemo__1_25_11_Questions
Use Firefox, Safari or Chrome or change settings for IE8
Don't have time to take the test, see what the results and instructor feedback look like.
1. Task A can start immediately and has a 4 day duration. Task B can start after A is complete and has a 7 day duration. Task C can start when A is complete and has a 5 day duration. Task D can start when B and C are complete and has a 6 day duration. Task E can start when D is complete and it has a 3 day duration. What is the duration of the project? (1015)
2. Which one of these is true of AON diagrams?
3. You are managing a project in a strong matrix organization and considering the contract types to use in an RFP for computer equipment. What is the best type of contract to use?
4. You take over a troubled project from a recently transferred project manager and want to address stakeholders' complaints that they have been kept in the dark about the project status. You should review what document(s) to correct this problem? (617)
5. Define scope does NOT use which of the following inputs: (034)