Last month, over 44,000 project professionals from 179 countries came to 4PM.com to improve their skills. 
 

How to Build the WBS

By Dick Billows, PMP, GCA

We don't build the work breakdown structure by making a list of all the things that sound good or that people ask for. We start the WBS with the scope statement and then decompose it into major deliverables. Then we meet with the project stakeholders. We need to uncover the requirements of our stakeholders and sponsor in order to have sufficient detail about deliverables that we can complete the WBS.

 

We use the WBS to drive a host of project management activities such as risk management, quality management, communications management, time and cost management. We gather requirements at the beginning of our project planning phase because they are necessary for many other project management tasks.
We can gather our project requirements very simply or have a much more elaborate requirements process where we are tracing the originator of each requirement and tying it to their performance commitments.

The consequences include stakeholders any additional requirements every single week.  This is the classic form of scope creep where we continue to add new features bells and whistles to the project.  This process also substantially increases the project failure rate because the project manager is not given additional time or resources to fulfill those requirements and dust the project is late and over budget.

How to build the work breakdown structure

 Step number

 Responsibility of

 Actions to take

1

 project manager and sponsor

 Finalize approval of the scope statement. Everything should be defined in  objectively measurable  terms

2

 project manager and stakeholders

 Decompose the scope into 4 to 7 objectively measurable deliverables. Each major deliverable should have acceptance criteria which allows us to objectively decide whether the deliverable has been produced or not

3

 project manager and team members

 Further, decompose the major deliverables down to the level of assignments for individuals that are generally 4 to 7 days worth of work. More capable individuals would get larger assignments and less experienced individuals would get smaller assignments

4

 project manager

 Develop a work package for each task in the work breakdown structure that will be assigned to an individual or contractor. The work package should contain information about:

  1. documentation requirements
  2.  input deliverables
  3.  output deliverables
  4.  major positive risks
  5.  major negative risks

5

 project manager and accountable team member

 Project manager and team member will be accountable for each task, meet to discuss the assignment. They identify the major positive risks and negative risks and the inputs the team member requires before he or she can start.

6

 

 when the team member accepts the work package for task, the WBS is complete and the team can move forward with estimating and scheduling

Deep Dive on this Topic With Additional Articles:

How To Construct a Work Breakdown Structure

Is Your WBS Designed for Success?